news

  • show moreshow less

    Pri Mlynoch – Construction Update

    12. 5. 2026

    We have successfully completed the key foundation stages at the Pri Mlynoch construction site. Although these works are less visible from the street, they are progressing with great intensity.

    Following the completion of all piling and the excavation shoring, we secured the walls with anchoring to achieve full watertightness. We are currently working below the groundwater level, where we are meticulously installing the substructure waterproofing. We are now heading towards the final step of this phase – pouring the foundation slab, which will serve as the solid pillar of the entire project.

    copy link
  • show moreshow less

    Excavation works are progressing smoothly and according to schedule.

    30. 1. 2026

    The underground sealing wall has been successfully completed, and anchoring works have begun.

    Contractors: Soletanche Bachy and Kobera NAD

    copy link
  • show moreshow less

    Pri Mlynoch has commenced construction work.

    3. 10. 2025

     

    The construction of the project started with the excavation and stabilization of the construction pit in the 41st week, based on a valid building permit for these parts of the project.

    The execution of the construction pit and special foundation works is expected to take 5-6 months, with the foundational slab and superstructure planned to follow in February/March 2025.

    Currently, a selection process is underway to choose the main contractor for the construction.

    You can read more in the article: https://www.yimba.sk/pri-mlynoch/bratislava-dostane-novu-vezu-iuris-startuje-vystavbu-projektu-pri-mlynoch-prace-zacinaju-o-par-dni

    copy link
  • show moreshow less

    N!DO is getting a new phase

    4. 9. 2025

    The third phase of the N!DO project is gradually becoming a reality.

    There are currently ongoing discussions regarding the layout ot he mass and architectural continuity with the previous phases, utilizing similar architectural elements. The project is being led by Ateliér Grido architects together with the Pantograph studio.
    The anticipated start of construction could be in 2027.

    You can read more in the article: https://www.yimba.sk/nido/jeden-z-najkrajsich-projektov-bratislavy-sa-rozsiri-ndo-dostane-novu-etapu-kvalitou-nema-zaostavat

     

    copy link
Map