Pri Mlynoch – Construction Update (2)
-
13. 7. 202613. 7. 2026
We are pleased to inform you of the smooth progress of construction work on our project.
Following the successful completion of the foundation slab and vertical load-bearing structures on the 2nd underground floor, we have moved to the next technological stage.
Currently, we have commenced the concreting of the ceiling slab over the 2nd underground floor. Concurrently, construction teams have advanced to the level above—on the 1st underground floor, intensive work is already underway on reinforcement, formwork installation, and the concreting of internal columns and load-bearing walls.
We are maintaining a steady pace, and construction works are progressing in accordance with the schedule.